" Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the... "
Cases Decided in the Court of Claims of the United States - Side 233
av United States. Court of Claims - 1939
Uten tilgangsbegrensning - Om denne boken

Cases Decided in the Court of Claims of the United States, Volum 111

United States. Court of Claims - 1948 - 886 sider
...concerning questions of fact arising under this contract shall be decided by the Contracting Officer, subject to written appeal by the Contractor within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision shall be final and conclusive...
Uten tilgangsbegrensning - Om denne boken

Decisions of the Comptroller General of the United States, Volum 29

United States. General Accounting Office - 1950 - 710 sider
...final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the contractor to the head of the department concerned or his duly authorized representative: whose decision on such appeal us to the facts of delay and the extension of time for completing the work shall be...
Uten tilgangsbegrensning - Om denne boken

United States Code Annotated, Volum 31

United States - 1927 - 682 sider
...cost shall be decided by Chief of Bureau subject to written appeal "by contractor to Secretary of Navy or his duly authorized representative whose decision shall be final and conclusive on parties, conscious wrongdoing or intention to cheat or be dishonest must be alleged and proved in...
Uten tilgangsbegrensning - Om denne boken

Decisions of the Comptroller General of the United States, Volum 8

United States. General Accounting Office - 1929 - 804 sider
...subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ARTICLE...
Uten tilgangsbegrensning - Om denne boken

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 sider
...subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ARTICLE...
Uten tilgangsbegrensning - Om denne boken

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 sider
...subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ART. 16....
Uten tilgangsbegrensning - Om denne boken

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 sider
...concerning questions of fact arising under this contract shall be decided by the Deputy Contracting 0fficer subject to written appeal by the Contractor within 30 days to the Chief of Engineers or his duly authorized representative whose decision shall be final and conclusive...
Uten tilgangsbegrensning - Om denne boken

Boulder Canyon Project: Final Reports

1950 - 1346 sider
...Contracting Officer, subject to written appeal by the City within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision shall be final and conclusive. Pending decision, the City shall diligently proceed with performance. ARTICLE 10— NONDISCRIMINATION...
Uten tilgangsbegrensning - Om denne boken

The Code of Federal Regulations of the United States of America ..., Bok 3

1939 - 1554 sider
...questions of fact arising under this contract shall be decided by the contracting officer subject to appeal by the contractor within 30 days to the head...be final and conclusive upon the parties thereto." (c) Director of Program Division. The Director of the Program Division is delegated the power to make...
Uten tilgangsbegrensning - Om denne boken

The Code of Federal Regulations of the United States of America ..., Volum 3

1939 - 1054 sider
...conclusive on the parties to the contract, subject only to appeal, within 30 days, by the contractor to the head of the department concerned, or his duly authorized representative? in connection with contracts on Standard Form No. 32, whose decision on such appeal as to the facts...