Sidebilder
PDF
ePub

5. Public Involvement: (Reference: Part 1506.6(3)-CEQ Regulations) Information regarding the policies of the Bureau of Prisons for implementing the NEPA process can be obtained from: Bureau of Prisons Facilities Development and Operations Office, 320 First Street, NW., Washington, DC 20534.

6. Supplemental Statements: (Reference: Part 1502.9(c)(3)-CEQ Regulations) If it is necessary to prepare a supplement to a Draft or Final Environmental Impact Statement, the supplement shall be introduced into the project administrative record.

7. Bureau of Prisons Decisionmaking Procedures: (Reference: Part 1501.1 (a) through (e)— CEQ Regulations) Major decision points likely to involve the NEPA process:

(1) Construction of a new Federal correctional institution.

(2) Closing of an existing Federal correctional institution.

(3) Activation of a surplus facility for conversion to a Federal correctional institution. (4) Significant change from the original mission of a Federal correctional institution.

(5) New construction at an existing Federal correctional institution which might significantly impact upon the existing community environment.

When the inclusion of certain voluminous data in environmental documents would prove impractical, the Bureau of Prisons will summarize the data and retain the original material as a part of its administrative record for the project. This material will be made available to the public in a central place to be designated in Environmental Impact Statements, and upon written request or court order copies of specified material will be provided. A charge may be made for copying, in accordance with current Department of Justice gudelines for reproduction of records.

Decisionmakers shall verify the consideration of all available options in the EIS with a comparative analysis of the alternatives to be considered in the decisionmaking process. 8. Those Actions Which Normally Do Require Environmental Impact Statements: (Reference: §1507.3(b)(2)(ii)—CEQ Regulations (1) New Federal correctional institution construction projects.

(2) Acquisition of surplus facilities for conversion to Federal correctional institutions, if the impact upon the quality of the human environment is likely to be significant.

(3) The closing of an existing Federal correctional institution, if that is likely to have a significant impact upon the quality of the human environment.

(4) Significant change from the original mission of a Federal correctional institution when the issue is likely to have an impact upon the quality of the human environment.

(5) New construction at an existing Federal correctional institution which would signifi

cantly affect the physical capacity, when the action is likely to have an impact upon the quality of the human environment.

(6) New construction at an existing Federal correctional institution which would significantly impact upon the quality of the community environment.

9. Those Actions Which Normally do not Require Either an Environmental Impact Statement or an Environmental Assessment: (Reference: Part 1507.3(b)(2)(ii) and Part 1508.4-CEQ Regulations) (1) Increase or decrease in population of a facility, above or below its physical capacity.

(2) Construction projects for existing facilities, including but not limited to: additions and remodeling; replacement of building systems and components; maintenance and operations, repairs, and general improvements; when such projects do not significantly alter the program of the facility or significantly impact upon the quality of the environment in the community.

(3) Contracts for halfway houses, community corrections centers, comprehensive sanction centers, community detention centers, or other similar facilities.

10. Those Actions Which Normally Require Environmental Assessments but not Necessarily Environmental Impact Statements: (Reference: $1507.3(b)(2)(iii)—CEQ Regulations) (1) Acquisition of surplus facilities for conversion to Federal correctional institution.

(2) Construction of additional facilities at an existing institution when the impact on the local environment is not seen to be significant, but when the alteration of programs or operations may be controversial.

(3) The closing of an institution or significant reduction in population of an institution when the impact on the local environment is not seen to be significant.

11. Emergency Actions: (Reference: Part 1506.11-CEQ Regulations). After consultation with the Council on Environmental Quality regarding alternative courses of action, the Bureau of Prisons may take action without observing the provisions of the CEQ Regulations and these Bureau of Prisons Procedures in the following cases:

(1) When the replacement of suddenly unavailable local utilities services, and/or resources, due to circumstances beyond the control of the Bureau of Prisons, is vital to the lives and safety of inmates and staff or protection of U.S. Government property.

(2) When unforeseen circumstances, such as greatly increased judicial commitments, suddenly dictate the activation of facilities to house increased numbers of Federal offenders and detainees significantly above the physical capacity of the combined Bureau of Prisons facilities in order to insure the lives and safety of inmates and staff or protection of U.S. Government property.

(3) When the sudden destruction of or damage to institutions dictates immediate replacement in order to protect the lives and safety of inmates and staff and protection of U.S. Government property.

12. Review.

(1) If a proposed action is not covered by Sections 8 through 10 of this appendix, the Bureau of Prisons will independently determine whether to prepare either an environmental impact statement or an environmental assessment.

(2) When a proposed action that could be classified as a categorical exclusion under Section 9 of this appendix involves extraordinary circumstances that may affect the environment, the Bureau shall conduct appropriate environmental studies to determine if the categorical exclusion classification is proper for that proposed action.

[Order No. 927-81, 46 FR 7953, Jan. 26, 1981, as amended by Order No. 2142-98, 63 FR 11121, Mar. 6, 1998]

(1) Actions normally requiring EIS

None

APPENDIX B TO PART 61-DRUG ENFORCEMENT ADMINISTRATION PROCEDURES RELATING TO THE IMPLEMENTATION OF THE NATIONAL ENVIRONMENTAL POLICY ACT

1. Applicability.

2. Typical Classes of Action Requiring Similar Treatment Under NEPA.

3. Environmental Information. 1. Applicability.

This part applies to all organizational elements of the Drug Enforcement Administration [DEA].

2. Typical Classes of Action Requiring Similar Treatment Under NEPA.

(a) Section 1507.3(c)(2) in conjunction with §1508.4 requires agencies to establish three typical classes of action for similar treatment under NEPA. These typical classes of action are set forth below:

(2) Actions normally not requiring environmental assessments or EIS (Categorical exclusions)

Scheduling of drugs as controlled substances

Establishing quotas for controlled substances. Registration of persons authorized to handle controlled substances.

Storage and destruction of controlled substances. Manual eradication of plant species from which controlled substances may be extracted.

(3) Actions normally requiring environmental assessments but not necessarily EIS

Chemical eradication of plant species from which controlled substances may be extracted.

[blocks in formation]

Air Act, as amended (42 U.S.C. 7609), and Executive Order 11514, Protection and Enhancement of Environmental Quality (March 5, 1970, as amended by Executive Order 11991, May 24, 1977).

2. Purpose. These procedures shall apply to efforts associated with the leasing, purchase, design, construction, and maintenance of new and existing INS facilities. All activities concerning the Immigration and Naturalization Service's compliance with NEPA shall be coordinated with Central Office Engineering staff.

3. Agency Description. The INS administers and enforces the immigration and nationality laws. This includes determining the admissibility of persons seeking entry into the United States and adjudicating requests for benefits and privileges under the immigration and nationality laws. The enforcement actions of INS involve the prevention of illegal entry of persons into the United States and the investigation and apprehension of aliens already in the country who because of inadmissibility at entry or misconduct committed following entry may be subject to deportation.

In carrying out its statutory enforcement responsibilities. the INS is authorized to arrest and detain aliens believed to be deportable and to effectuate removal from the U.S. of aliens found deportable after hearing.

4. Designation of Responsible Official. The Chief Engineer, Facilities and Engineering Branch shall be the liasion official for INS with the Council on Environmental Quality, the Environmental Protection Agency, and the other departments and agencies concerning environmental matters. Duties of the Chief Engineer include:

(a) Insuring compliance with the requirements of NEPA and that the actions with respect to the fulfillment of NEPA are coordinated;

(b) Providing for procedural and substantive training on environmental issues, policy, procedures and clearance requirements;

(c) Providing guidance in the preparation and processing of Environmental Impact

Statements; and

(d) Participating in policy formulation, as necessary, in the application of the requirements of the National Environmental Policy Act of 1969.

5. NEPA and INS Planning. (a) INS will make available to the public proposals and feasibility studies for facilities under consideration for possible use as INS facilities.

(b) Interested parties indentified as such by the local clearinghouse (as established by the Office of Management and Budget Circular No. A-95) will be advised and informed concerning proposed plans which might involve NEPA regulations.

(c) Upon completion of the preliminary groundwork described above, INS will issue an A-95 Letter of Intent to:

(1) File an Environmental Impact Assessment (EIA);

(2) File an Environmental Impact Statement (EIS). (Reference: 1501.2-CEQ Regulations.)

6. Public Involvement. Information regarding the policies of INS for implementing the NEPA process can be obtained from: Immigration and Naturalization Service, Facilities and Engineering Branch, 425 I Street NW.. Washington, DC 20536. (Reference: Part 1506.6(3)-CEQ Regulations.)

7. Supplemental Statements. If it is necessary to prepare a supplement to a draft or a Final Environmental Impact Statement, the supplement shall be introduced into the administrative record pertaining to the project. (Reference: Part 1502.9(c)(3)-CEQ Regulations.)

8. INS Decisionmaking Procedure. (a) Policy(1) The Chief Engineer will consider all practical means, including the "no-action" alternative and other alternatives to the proposed action, which will enhance, protect, and preserve the quality of the environment, restore environmental quality previously lost, and minimize and mitigate unavoidable adverse effects. He will analyze and study the environment together with engineering, economic, social and other considerations to insure balanced decisionmaking in the overall public interest.

(2) During INS project planning and the related decisonmaking process, environmental effects will be weighed together with the engineering, economic and social and other considerations affecting the public interest.

(b) Preparation of the environmental impact statements. (1) Situations where Environmental Impact Statements (EIS) are required are described in section 102(2)(C) of NEPA. EIS constitute an integral of the plan formulation process and serve as a summation and evaluation of the effects, both beneficial and adverse, that each alternative action would have on the environment, and as an explanation and objective evaluation of the plan which is finally recommended.

(2) Should the Chief Engineer determine in assessing the impact of a minor action that an environmental statement is not required, the determination to that effect will be placed in the project file. This negative determination shall be made available to the public as required in § 1506.6 of the CEQ regulations and shall include a statement of the facts and the basis for the decision.

(3) When inclusion of certain voluminous data in an EIS would prove to be impractical, INS will summarize the data and retain the original material as a part of its administrative record for the project. This material will be made available to the public in a central place to be designated in the EIS,

197-102 D-6

and upon written request or court order, copies of specified material will be provided. A charge for the reproduction of records may be made in accordance with current Department of Justice guidelines. (Reference: Part 1505 CEQ Regulations.)

9. Actions Which Normally Do Require Environmental Impact Statements: (a) Construction of a new INS facility which would have a significant impact upon the environment.

(b) Construction of a new addition to an existing INS facility which would significantly affect the physical capacity and which would have a significant impact upon the environment. (Reference:

§ 1507.3(b)(2)(i)-CEQ Regulations.)

10. Actions Which Normally Do Not Require Either An Environmental Impact Statement Or An Environmental Assessment: (a) Construction projects for existing facilities including but not limited to: Remodeling; replacement of building systems and components; maintenance and operations repairs and general improvements when such projects do not significantly alter the intitial occupancy and program of the facility or significantly impact upon the environment.

(b) Increase or decrease in population of a facility within its physical capacity. (Reference: Part 1507.3(b)(2)(ii) and Part 1508.4CEQ Regulations.)

11. Actions Which Normally Require An Environmental Assessment But Not Necessarily Environmental Impact Statements:

(a) Construction of a new addition to an existing INS facility which may affect the physical capacity and may have some impact upon the environment.

(b) Closing of an INS facility which may have some impact on the environment. (Reference: § 1507.3(b)(2)(iii)—CEQ Regulations.)

APPENDIX D TO PART 61-OFFICE OF JUSTICE ASSISTANCE, RESEARCH, AND STATISTICS PROCEDURES RELATING TO THE IMPLEMENTATION OF THE NATIONAL ENVIRONMENTAL POLICY Аст

1. AUTHORITY

These procedures are issued pursuant to the National Environmental Policy Act (NEPA) of 1969, 42 U.S.C. 4321, et seq., Regulations of the Council on Environmental Quality, 40 CFR part 1500, et seq., the Environmental Quality Improvement Act of 1970, as amended, 42 U.S.C. 4371, et seq., Section 309 of the Clean Air Act, as amended, 42 U.S.C. 7609, and Executive Order 11514, "Protection and Enhancement of Environmental Quality," March 5, 1970, as amended by Executive Order 11991, March 24, 1977.

2. PURPOSE

It is the purpose of these procedures to supplement the procedures of the Depart

ment of Justice so as to insure compliance with NEPA. These procedures supersede the regulations contained in 28 CFR part 19.

3. AGENCY DESCRIPTION

The Office of Justice Assistance, Research, and Statistics (OJARS) assists State and local units of government in strengthening and improving law enforcement and criminal justice by providing financial assistance and funding research and statistical programs. OJARS will coordinate the activities and provide the staff support for three Department of Justice Federal financial assistance offices: the Law Enforcement Assistance Administration, the National Institute of Justice, and the Bureau of Justice Statistics. Each of the assistance offices has the authority to award grants, contracts and cooperative agreements pursuant to the Justice System Improvement Act of 1979, Public Law 96– 157 (December 27, 1979).

4. TYPICAL CLASSES OF ACTION UNDERTAKEN (a) Actions which normally require an environmental impact statement.

(1) None.

(b) Actions which normally do not require either an environmental impact statement or an environmental assessment.

(1) The bulk of the funded efforts; training programs, court improvement projects, research, and gathering statistical data.

(2) Minor renovation projects or remodeling.

(c) Actions which normally require environmental assessments but not necessarily environmental impact statements.

(1) Renovations which change the basic prior use of a facility or significantly change the size.

(2) New construction.

(3) Research and technology whose anticipated and future application could be expected to have an effect on the environment. (4) Implementation of programs involving the use of chemicals.

(5) Other actions in which it is determined by the Administrator. Law Enforcement Assistance Administration; the Director, Bureau of Justice Statistics; or the Director, National Institute of Justice, to be necessary and appropriate.

5. AGENCY PROCEDURES

An environmental coordinator shall be designated in the Bureau of Justice Statistics, the Law Enforcement Assistance Administration, and in the National Institute of Justice. Duties of the environmental coordinator shall include:

(a) Insuring that adequate environmental assessments are prepared at the earliest possible time by applicants on all programs or projects that may have a significant impact on the environment. The assessments shall

contain documentation from independent parties with expertise in the particular environmental matter when deemed appropriate. The coordinator shall return assessments that are found to be inadequate.

(b) Reviewing the environmental assessments and determining whether an Environmental Impact Statement is required or preparing a "Finding of No Significant Impact.”

(c) Coordinating the efforts for the preparation of an Environmental Impact Statement consistent with the requirements of 40 CFR part 1502.

(d) Cooperating and coordinating efforts with other Federal agencies.

(e) Providing for agency training on environmental matters.

6. COMPLIANCE WITH OTHER ENVIRONMENTAL STATUTES

To the extent possible an environmental assessment, as well as an environmental impact statement, shall include information necessary to assure compliance with the following:

Fish and Wildlife Coordination Act, 16 U.S.C. 661, et seq.; the National Historic Preservation Act of 1966, 16 U.S.C. 470, et seq.; Flood Disaster Protection Act of 1973, 42 U.S.C. 400, et seq.; Clean Air Act and Federal Water Pollution Control Act, 42 U.S.C. 1857, et seq.; 33 U.S.C. 1251, et seq.; Safe Drinking Water Act, 42 U.S.C. 300, et seq.; Wild and Scenic Rivers Act, 16 U.S.C. 1271, et seq.; the Coastal Zone Management Act of 1972, 16 U.S.C. 1451, et seq.; and other environmental review laws and executive orders.

7. ACTIONS PLANNED BY PRIVATE APPLICANTS OR OTHER NON-FEDERAL ENTITIES

Where actions are planned by private applicants or other non-Federal entities before Federal involvement:

(a) The Policy and Management Planning Staff, Office of Criminal Justice Programs, LEAA, Room 1158B, 633 Indiana Ave., Washington, DC 20531, Telephone: 202/724-7659, will be available to advise potential applicants of studies or other information foreseeably required for later Federal action;

(b) OJARS will consult early with appropriate State and local agencies and with interested private persons and organizations when its own involvement is reasonably foreseeable;

(c) OJARS will commence its NEPA process at the earliest possible time (Ref. §1501.2(d) CEQ Regulations).

8. SUPPLEMENTING AN EIS

If it is necessary to prepare a supplement to a draft or a final EIS, the supplement shall be introduced into the administrative record pertaining to the project. (Ref. §1502.9(c)(3) CEQ Regulations).

[blocks in formation]

(a) It is the Department of Justice's policy to avoid to the extent possible the long and short term adverse impacts associated with the destruction or modification of wetlands and floodplains and to avoid direct or indirect support of new construction in floodplains and wetlands whenever there is a practicable alternative. The Department will provide leadership and take affirmative action to carry out the Orders.

(b) It is the Department of Justice's intention to integrate these procedures with those required under statutes protecting the environment, such as the National Environmental Policy Act (NEPA). Whenever possible, the procedures detailed herein should be coordinated with other required documents, such as the environmental impact

« ForrigeFortsett »