vative design, life-cycle costs, and other pertinent factors, of incorporating such items in the system.

(e) PROTEST FILE.-(1) If, in the case of a solicitation for a contract issued by, or an award or proposed award of a contract by, the head of an agency, a protest is filed pursuant to the procedures in subchapter V of chapter 35 of title 31 and an actual or prospective offeror so requests, a file of the protest shall be established by the procuring activity and reasonable access shall be provided to actual or prospective offerors.

(2) Information exempt from disclosure under section 552 of title 5 may be redacted in a file established pursuant to paragraph (1) unless an applicable protective order provides otherwise.

(3) Regulations implementing this subsection shall be consistent with the regulations regarding the preparation and submission of an agency's protest file (the so-called "rule 4 file") for protests to the General Services Board of Contract Appeals under section 111 of the Federal Property and Administrative Services Act of 1949 (41 U.S.C. 759).

(f) AGENCY ACTIONS ON PROTESTS.-If, in connection with a protest, the head of an agency determines that a solicitation, proposed award, or award does not comply with the requirements of law or regulation, the head of the agency

(1) may take any action set out in subparagraphs (A) through (F) of subsection (b)(1) of section 3554 of title 31; and

(2) may pay costs described in paragraph (1) of section 3554(c) of title 31 within the limits referred to in paragraph (2) of such section.

(Aug. 10, 1956, ch. 1041, 70A Stat. 130; revised in its entirety July 18, 1984, P.L. 98-369, $2723(b), 98 Stat. 1191; amended Oct. 19, 1984, P.L. 98–525, § 1213(a), 98 Stat. 2591; P.L. 99145, 1303(a)(14), Nov. 8, 1985, 99 Stat. 739; Nov. 14, 1986, P.L. 99-661, §313(b), 100 Stat. 3932; amended identically P.L. 99-500, 99-591, 99–661, §§ 101(c) (§ 924 (a), (b)], 101(c) (§ 924 (a), (b)], 924 (a), (b), Oct. 18, Oct. 30, Nov. 14, 1986, 100 Stat. 1783-153, 3341-153, 3853, amended P.L. 100-456, §806, Sept. 29, 1988, 102 Stat. 2010; P.L. 101-189, 8853(f), Nov. 29, 1989, 103 Stat. 1519; P.L. 101-510, §802, Nov. 5, 1990, 104 Stat. 1588; P.L. 103-160, 1182(a)(5), Nov. 30, 1993, 107 Stat. 1771; P.L. 103-355, §§ 1011, 1012, 1013, 1014, 1015, 1016, 4401(b), Oct. 13, 1994, 108 Stat. 3254, 3255, 3256, 3257, 3347.)

[§ 2305a. Transferred to § 2438]

82306. Kinds of contracts

(a) The cost-plus-a-percentage-of-cost system of contracting may not be used. Subject to the limitation in the preceding sentence, the other provisions of this section, and other applicable provisions of law, the head of an agency, in awarding contracts under this chapter after using procedures other than sealed-bid procedures, may enter into any kind of contract that he considers will promote the best interests of the United States.

(b) Each contract awarded under this chapter after using procedures other than sealed-bid procedures shall contain a warranty, determined to be suitable by the head of the agency, that the contractor has employed or retained no person or selling agency to solicit or obtain the contract under an understanding or agreement for a commission, percentage, brokerage, or contingent fee, except a bona fide employee or established commercial or selling agency maintained by him to obtain business. If a contractor breaks such a warranty the United States may annul the contract without liability or may deduct the commission, percentage, brokerage, or

contingent fee from the contract price or consideration. This subsection does not apply to a contract that is for an amount not greater than the simplified acquisition threshold or to a contract for the acquisition of commercial items.

[(c) Repealed. P.L. 103–355, § 1021, 108 Stat. 3257]

(d) The fee for performing a cost-plus-a-fixed-fee contract for experimental, developmental, or research work may not be more than 15 percent of the estimated cost of the contract, not including the fee. The fee for performing a cost-plus-a-fixed-fee contract for architectural or engineering services for a public work or utility plus the cost of those services to the contractor may not be more than 6 percent of the estimated cost of that work or project, not including fees. The fee for performing any other cost-plus-a-fixed-fee contract may not be more than 10 percent of the estimated cost of the contract, not including the fee. Determinations under this subsection of the estimated costs of a contract or project shall be made by the head of the agency at the time the contract is made.

(e) Each cost contract and each cost-plus-a-fixed-fee contract shall provide for notice to the agency by the contractor before the making, under the prime contract, of

(1) a cost-plus-a-fixed-fee subcontract; or

(2) a fixed-price subcontract or purchase order involving more than the greater of (A) the simplified acquisition threshold, or (B) 5 percent of the estimated cost of the prime contract. (f) So-called "truth-in-negotiations" provisions relating to cost or pricing data to be submitted by certain contractors and subcontractors are provided in section 2306a of this title.

(g)(1) The head of an agency may enter into contracts for periods of not more than five years for the following types of services (and items of supply related to such services) for which funds would otherwise be available for obligation only within the fiscal year for which appropriated

(A) operation, maintenance, and support of facilities and installations;

(B) maintenance or modification of aircraft, ships, vehicles, and other highly complex military equipment;

(C) specialized training necessitating high quality instructor skills (for example, pilot and aircrew members; foreign language training); and

(D) base services (for example, ground maintenance; inplane refueling; bus transportation; refuse collection and disposal);

whenever he finds that

(i) there will be a continuing requirement for the services consonant with current plans for the proposed contract period;

(ii) the furnishing of such services will require a substantial initial investment in plant or equipment, or the incurrence of substantial contingent liabilities for the assembly, training, or transportation of a specialized work force; and

(iii) the use of such a contract will promote the best interests of the United States by encouraging effective competition and promoting economies in operation.

(2) In entering into such contracts, the head of the agency shall be guided by the following principles:

(A) The portion of the cost of any plant or equipment amortized as a cost of contract performance should not exceed the ratio between the period of contract performance and the anticipated useful commercial life of such plant or equipment. Useful commercial life, for this purpose, means the commercial utility of the facilities rather than the physical life thereof, with due consideration given to such factors as location of facilities, specialized nature thereof, and obsolescence.

(B) Consideration shall be given to the desirability of obtaining an option to renew the contract for a reasonable period not to exceed three years, at prices not to include charges for plant, equipment and other nonrecurring costs, already amortized.

(C) Consideration shall be given to the desirability of reserving in the agency the right, upon payment of the unamortized portion of the cost of the plant or equipment, to take title thereto under appropriate circumstances.

(3) In the event funds are not made available for the continuation of such a contract into a subsequent fiscal year, the contract shall be canceled or terminated, and the costs of cancellation or termination may be paid from

(A) appropriations originally available for the performance of the contract concerned;

(B) appropriations currently available for procurement of the type of services concerned, and not otherwise obligated; or (C) funds appropriated for those payments.

(h) Multiyear contracting authority is provided in section 2306b of this title.

(Aug. 10, 1956, ch. 1041, 70A Stat. 130; Sept. 10, 1962, P.L. 87-653, § 1(d), (e), 76 Stat. 528; July 5, 1968, P.L. 90-378, § 1, 82 Stat. 289; Sept. 25, 1968, P.L. 90-512, 82 Stat. 863; Dec. 12, 1980, P.L. 96-513, §511(77), 94 Stat. 2926; Dec. 1, 1981, P.L. 97-86, §§ 907(b), 909(b), 95 Stat. 1117, 1118; July 18, 1984, P.L. 98-369, 82724, 98 Stat. 1192; Nov. 8, 1985, P.L. 99-145, § 1303(a)(15), 99 Stat. 739; amended identically P.L. 99-500, 99-591, 99-661, §§ 101(c) [§ 952 (b), (c)], 101(c) [§ 952 (b), (c)], 952 (b), (c), Oct. 18, Oct. 30, Nov. 14, 1986, 100 Stat. 1783-169, 3341169, 3949; P.L. 101-189, §805(a), Nov. 29, 1989, 103 Stat. 1488; P.L. 101-510, §808, Nov. 5, 1990, 104 Stat. 1593; P.L. 102-25, §701(d)(3), April 6, 1991, 105 Stat. 114; P.L. 103-355, §§ 1021, 1022(b), 4102(b), 4401(c), 8105(a), Oct. 13, 1994, 108 Stat. 3257, 3260, 3340, 3348, 3392.)

§ 2306a. Cost or pricing data: truth in negotiations

(a) REQUIRED COST OR PRICING DATA AND CERTIFICATION.-(1) The head of an agency shall require offerors, contractors, and subcontractors to make cost or pricing data available as follows:

(A) An offeror for a prime contract under this chapter to be entered into using procedures other than sealed-bid procedures shall be required to submit cost or pricing data before the award of a contract if—

(i) in the case of a prime contract entered into after December 5, 1990, the price of the contract to the United States is expected to exceed $500,000; and

(ii) in the case of a prime contract entered into on or before December 5, 1990, the price of the contract to the United States is expected to exceed $100,000.

(B) The contractor for a prime contract under this chapter shall be required to submit cost or pricing data before the pricing of a change or modification to the contract if—

(i) in the case of a change or modification made to a prime contract referred to in subparagraph (A)(i), the price adjustment is expected to exceed $500,000;

(ii) in the case of a change or modification made after December 5, 1991, to a prime contract that was entered into on or before December 5, 1990, and that has been modified pursuant to paragraph (6), the price adjustment is expected to exceed $500,000; and

(iii) in the case of a change or modification not covered by clause (i) or (ii), the price adjustment is expected to exceed $100,000.

(C) An offeror for a subcontract (at any tier) of a contract under this chapter shall be required to submit cost or pricing data before the award of the subcontract if the prime contractor and each higher-tier subcontractor have been required to make available cost or pricing data under this section and

(i) in the case of a subcontract under a prime contract referred to in subparagraph (A)(i), the price of the subcontract is expected to exceed $500,000;

(ii) in the case of a subcontract entered into after December 5, 1991, under a prime contract that was entered into on or before December 5, 1990, and that has been modified pursuant to paragraph (6), the price of the subcontract is expected to exceed $500,000; and

(iii) in the case of a subcontract not covered by clause (i) or (ii), the price of the subcontract is expected to exceed $100,000.

(D) The subcontractor for a subcontract covered by subparagraph (C) shall be required to submit cost or pricing data before the pricing of a change or modification to the subcontract if

(i) in the case of a change or modification to a subcontract referred to in subparagraph (C)(i) or (C)(ii), the price adjustment is expected to exceed $500,000; and

(ii) in the case of a change or modification to a subcontract referred to in subparagraph (C)(iii), the price adjustment is expected to exceed $100,000.

(2) A person required, as an offeror, contractor, or subcontractor, to submit cost or pricing data under paragraph (1) (or required by the head of the agency concerned to submit such data under subsection (c)) shall be required to certify that, to the best of the person's knowledge and belief, the cost or pricing data submitted are accurate, complete, and current.

(3) Cost or pricing data required to be submitted under paragraph (1) (or under subsection (c)), and a certification required to be submitted under paragraph (2), shall be submitted

(A) in the case of a submission by a prime contractor (or an offeror for a prime contract), to the contracting officer for the contract (or to a designated representative of the contracting officer); or

(B) in the case of a submission by a subcontractor (or an offeror for a subcontract), to the prime contractor.

(4) Except as provided under subsection (b), this section applies to contracts entered into by the head of an agency on behalf of a foreign government.

(5) For purposes of paragraph (1)(C), a contractor or subcontractor granted a waiver under subsection (b)(1)(B) shall be considered as having been required to make available cost or pricing data under this section.

(6) Upon the request of a contractor that was required to submit cost or pricing data under paragraph (1) in connection with a prime contract entered into on or before December 5, 1990, the head of the agency that entered into such contract shall modify the contract to reflect subparagraphs (B)(ii) and (C)(ii) of paragraph (1). All such modifications shall be made without requiring consideration.

(7) Effective on October 1 of each year that is divisible by 5, each amount set forth in paragraph (1) shall be adjusted to the amount that is equal to the fiscal year 1994 constant dollar value of the amount set forth. Any amount, as so adjusted, that is not evenly divisible by $50,000 shall be rounded to the nearest multiple of $50,000. In the case of an amount that is evenly divisible by $25,000 but not evenly divisible by $50,000, the amount shall be rounded to the next higher multiple of $50,000.

(b) EXCEPTIONS.

(1) IN GENERAL.-Submission of cost or pricing data shall not be required under subsection (a) in the case of a contract, a subcontract, or modification of a contract or subcontract(A) for which the price agreed upon is based on

(i) adequate price competition;

(ii) established catalog or market prices of commercial items that are sold in substantial quantities to the general public; or

(iii) prices set by law or regulation; or

(B) in an exceptional case when the head of the procuring activity, without delegation, determines that the requirements of this section may be waived and justifies in writing the reasons for such determination.

(2) MODIFICATIONS OF CONTRACTS AND SUBCONTRACTS FOR COMMERCIAL ITEMS.-In the case of a modification of a contract or subcontract for a commercial item that is not covered by the prohibition on the submission of cost or pricing data in paragraph (1)(A), submission of cost or pricing data shall not be required under subsection (a) if

(A) the contract or subcontract being modified is a contract or subcontract for which submission of cost or pricing data may not be required by reason of paragraph (1)(A); and

(B) the modification would not change the contract or subcontract, as the case may be, from a contract or subcontract for the acquisition of a commercial item to a contract or subcontract for the acquisition of an item other than a commercial item.

« ForrigeFortsett »