19. Touchet Division, Walla Walla Project, Oregon-Washington

43 U.S.C. 616

§ 616tttt. Authorization for construction, operation, and maintenance.

(a) Purposes; principal works.

For purposes of supplying irrigation water initially for approximately ten thousand acres of land, providing municipal and industrial water, flood control, the enhancement of fish and wildlife resources, and the enhancement of recreation opportunities, the Secretary of the Interior (hereinafter referred to as the Secretary) is authorized to construct, operate, and maintain the Touchet division of the Walla Walla project, Oregon-Washington, in accordance with the Federal reclamation laws (Act of June 17, 1902, 32 Stat. 388, and Acts amendatory thereof or supplementary thereto). The principal works of the division (hereinafter referred to as the project) shall consist of the Dayton Dam and Reservoir, fish passage facilities, a diversion dam, and associated drainage facilities.

[blocks in formation]

(c) Maintenance of streamflow to insure fish and wildlife conservation.

In order to assure a realization of the fish and wildlife enhancement benefits contemplated by sections 616tttt to 616yyyy of this title, the Secretary shall adopt appropriate measures to insure the maintenance of a streamflow between Dayton Dam and the mouth of the Walla Walla River that is not less than thirty cubic feet per second unless he determines that a water shortage or other emergencies exist or that lesser flows would be adequate for the maintenance of fish life. (Pub. L. 91-307, § 1, July 7, 1970, 84 Stat. 409.)

[merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small]
[merged small][merged small][merged small][ocr errors][merged small][merged small][merged small]

§ 616yyyy. Authorization of appropriations. (a) Separable and joint construction costs allocable to enhancement of anadromous fish.

There are authorized to be appropriated to the United States Fish and Wildlife Service, for transfer to the Bureau of Reclamation, such sums as may be required to cover separable and joint construction costs of the Touchet division, Walla Walla project, allocable to the enhancement of anadromous fish as determined by cost allocation studies comparable to those set forth in House Document Numbered 155, Eighty-ninth Congress, second session.

(b) Construction of works involved in Touchet division.

There are authorized to be appropriated to the Bureau of Reclamation for construction of the works involved in the Touchet division $22,774,000 (January 1969 prices), less the amounts authorized by subsection (a) of this section.

(c) Adjustment of appropriated amounts.

The total sums authorized to be appropriated by subsection (a) and subsection (b) of this section shall be plus or minus such amounts, if any, as may be required by reason of changes in the cost of construction work of the types involved therein as shown by engineering cost indexes, and, in addition thereto, such sums as may be required to operate and maintain such division: Provided, That funds appropriated pursuant to the authority contained in subsection (b) of this section shall be expended only if the amount thereof is increased in any given fiscal year by a proportionate amount appropriated pursuant to subsection (a) of this section. (Pub. L. 91-307, § 6, July 7, 1970, 84 Stat. 410.)

SECTION REFERRED TO IN OTHER SECTIONS This section is referred to in sections 616tttt. 616xxxx of this title.

20. Garrison Diversion Unit, Missouri River Basin Project, North Dakota

South Dakota

Act of August 5, 1965, P.L. 89-108 (79 Stat. 433-435)

AN ACT

To make certain provisions in connection with the construction of the Garrison diversion unit, Missouri River Basin project, by the Secretary of the Interior.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the general plan for the Missouri-Souris unit of the Missouri River Basin

project, heretofore authorized in section 9 of the Flood Control Act of December 22, 1944 (58 Stat. 887), as modified by the report of the Secretary of the Interior contained in House Document Numbered 325, Eighty-sixth Congress, second session, is confirmed and approved under the designation "Garrison diversion unit," and the construction of a development providing for the irrigation of two hundred and fifty thousand acres, municipal and industrial water, fish and wildlife conservation and development, recreation, flood control, and other project purposes shall be prosecuted by the Department of the Interior substantially in accordance with the plans set out in the Bureau of Reclamation report dated November 1962 (revised February 1965) supplemental report to said House Document Numbered 325.

SEC. 2. (a) Subject to the provisions of subsections (b), (c), (d), and (e) of this section, the Secretary is authorized in connection with the Garrison diversion unit (i) to construct, operate, and maintain or provide for the construction, operation, and maintenance of public outdoor recreation and fish and wildlife enhancement facilities, (ii) to acquire or otherwise to include within the unit area such adjacent lands or interests in land as are necessary for present or future public recreation or fish and wildlife use, (iii) to allocate water and reservoir capacity to recreation and fish and wildlife enhancement, and (iv) to provide for the public use and enjoyment of unit lands, facilities, and water areas in a manner coordinated with other unit purposes. The Secretary is further authorized to enter into agreements with Federal agencies or State or local public bodies for the operation, maintenance, and replacement of unit facilities, and to transfer unit lands or facilities to Federal agencies or State or local public bodies by lease or exchange, upon such terms and conditions as will best promote the development and operation of such lands or facilities in the public interest for recreation and fish and wildlife enhancement purposes.

(b) All costs allocated to fish and wildlife enhancement and incurred in connection with waterfowl refuges and waterfowl production areas proposed for Federal administration shall be nonreimbursable.

(c) (1) If, before commencement of construction of the unit, non-Federal public bodies agree to administer for recreation or fish and wildlife enhancement or for both of these purposes pursuant to the plan for the development of the unit approved by the Secretary, land and water areas which are not included within Federal waterfowl refuges and waterfowl production areas and to bear not less than one-half the separable costs of the unit allocated to either or both of said purposes, as the case may be, and attributable to such areas and all the costs of operation, maintenance, and replacement incurred in connection therewith, the remainder of the separable capital costs so allocated and attributed shall be nonreimbursable.

(2) In the absence of such a preconstruction agreement, recreation and fish and wildlife enhancement facilities (other than minimum facilities for the public health and safety at reservoir access points and facilities related to Federal waterfowl refuges and waterfowl production areas) shall not be provided, and the allocation of unit costs shall reflect only the number of visitor days

and the value per visitor day estimated to result from such diminished recreation development without reference to lands which may be provided pursuant to subsection (e) of this section.

(d) The non-Federal share of the separable capital costs of the unit allocated to recreation and fish and wildlife enhancement shall be borne by non-Federal interests, under either or both of the following methods as may be determined appropriate by the Secretary: (i) payment, or provision of lands, interests therein, or facilities for the unit; or (ii) repayment, with interest, within fifty years of first use of unit recreation or fish and wildlife enhancement facilities: Provided, That the source of repayment may be limited to entrance and user fees or charges collected at the unit by non-Federal interests if the fee schedule and the portion of fees dedicated to repayment are established on a basis calculated to achieve repayment as aforesaid and are made subject to review and renegotiation at intervals of not more than five

years.

(e) Nothwithstanding the absence of preconstruction agreements as specified in subsection (c) of this section lands may be acquired in connection with construction of the unit to preserve the recreation and fish and wildlife enhancement potential of the unit.

(1) If non-Federal public bodies agree within ten years after initial unit operation to administer for recreation and fish and wildlife enhancement pursuant to the plan for development of the unit approved by the Secretary land and water areas which are not included within Federal waterfowl refuges and waterfowl production areas and to bear not less than one-half the costs of lands acquired therefor pursuant to this subsection and facilities and project modifications provided for those purposes and all costs of operation, maintenance, and replacement incurred therefor, the remainder of the costs of such lands, facilities, and project modifications shall be nonreimbursable. Such agreement and subsequent development shall not be the basis for any allocation of joint costs of the unit to recreation or fish and wildlife enhancement.

(2) If, within ten years after initial operation of the unit, there is not an executed agreement as specified in paragraph (1) of this subsection, the Secretary may utilize the lands for any lawful purpose within the jurisdiction of the Department of the Interior, or may transfer custody of the land to another Federal agency for use for any lawful purpose within the jurisdiction of that agency, or may lease the lands to a non-Federal public body, or may transfer the lands to the Administrator of General Services for disposition in accordance with the surplus property laws of the United States. In no case shall the lands be used or made available for use for any purpose in conflict with the purposes for which the project was constructed, and in every case preference shall be given to uses which will preserve and promote the recreation and fish and wildlife enhancement potential of the project or, in the absence thereof, will not detract from that potential.

(f) Subject to the limitations hereinbefore stated, joint capital costs allocated to recreation and fish and wildlife enhancement shall be nonreimbursable.

(g) Costs of means and measures to prevent loss

of and damage to fish and wildlife shall be treated as unit costs and allocated among all unit purposes. (h) As used in this Act, the term "nonreimbursable" shall not be construed to prohibit the imposition of entrance, admission, and other recreation user fees or charges.

SEC. 3. The Garrison diversion unit shall be integrated physically and financially with the other Federal works constructed or authorized to be constructed under the comprehensive plan approved by section 9 of the Act of December 22, 1944, as amended and supplemented. The Secretary shall give consideration to returning to the Missouri River to the fullest extent practicable such of the return flows as are not required for beneficial purposes.

SEC. 4. (a) The interest rate used for computing interest during construction and interest on the unpaid balance of the capital costs allocated to interest-bearing features of the Garrison diversion unit as authorized in this Act shall be determined by the Secretary of the Treasury as of the beginning of the fiscal year in which construction is initiated, on the basis of the computed average interest rate payable by the Treasury upon its outstanding marketable public obligations, which are neither due nor callable for redemption for fifteen years from date of issue.

(b) From and after July 1, 1965, the interest rate on the unamortized balance of the investment allocated to commercial power in facilities constructed or under construction on June 30, 1965, by

the Department of the Army in the Missouri River Basin, the commercial power from which is marketed by the Department of the Interior, and in the transmission and marketing facilities associated therewith, shall be 22 per centum per annum.

SEC. 5. For a period of ten years from the date of enactment of this Act, no water from the project authorized by this Act shall be delivered to any water user for the production on newly irrigated lands of any basic agricultural commodity, as defined in the Agricultural Act of 1949, or any amendment thereof, if the total supply of such commodity for the marketing year in which the bulk of the crop would normally be marketed is in excess of the normal supply as defined in section 301(b) (10) of the Agricultural Adjustment Act of 1938, as amended, unless the Secretary of Agriculture calls for an increase in production of such commodity in the interest of national security.

SEC. 6. There is hereby authorized to be appropriated for construction of the Garrison diversion unit as authorized in this Act, the sum of $207,000,000, plus or minus such amounts, if any, as may be justified by reason of ordinary fluctuations in construction costs as indicated by engineering cost indexes applicable to the types of construction involved herein. There are also authorized to be appropriated such additional sums as may be required for operation and maintenance of the unit.

Approved August 5, 1965.

21. Mid-State Division, Missouri River Basin Project, Nebraska Act of Nov. 17, 1965, P.L. 90-136 (81 Stat. 444 et seq.)

AN ACT

To authorize the Secretary of the Interior to construct, operate, and maintain the Nebraska Mid-State division, Missouri River Basin project, and for other purposes.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the Secretary of the Interior is hereby authorized to construct, operate, and maintain in accordance with the Federal reclamation laws (Act of June 17, 1902 (32 Stat. 388), and Acts amendatory thereof or supplementary thereto the Nebraska Mid-State division, Missouri River Basin project, Nebraska, for the principal purposes of furnishing a surface irrigation water supply for approximately one hundred and forty thousand acres of land, aiding in the replenishment of the ground water supply of the area for domestic and agricultural use, controlling floods, conserving and developing fish and wildlife, enhancing recreation opportunities, and producing hydroelectric power. The principal works of the project shall consist of a diversion dam on the Platte River, a main supply canal, an interconnected reservoir system, hydroelectric power facilities, wasteways, pumps, drains, canals, laterals, distribution facilities, and related works.

SEC. 2. The Nebraska Mid-State division shall be integrated, physically and financially, with the other Federal works in the Missouri River Basin constructed or authorized to be constructed under

the comprehensive plans approved by section 9 of the Act of December 22, 1944 (58 Stat. 891), as amended and supplemented, and shall be a division of the Missouri River Basin project therein approved and authorized.

SEC. 3. The interest rate used for computing interest during construction and interest on the unpaid balance of the capital costs allocated to interest-bearing features of the Nebraska Mid-State division shall be determined by the Secretary of the Treasury as of the beginning of the fiscal year in which construction is initiated, on the basis of the computed average interest rate payable by the Treasury upon its outstanding marketable public obligations, which are neither due nor callable for redemption for fifteen years from date of issue.

SEC. 4. For a period of ten years from the date of enactment of this Act, no water from the project authorized by this Act shall be delivered to any water user for the production on newly irrigated lands of any basic agricultural commodity, as defined in the Agricultural Act of 1949, or any amendment thereof, if the total supply of such commodity for the marketing year in which the bulk of the crop would normally be marketed is in excess of the normal supply as defined in section 301(b) (10) of the Agricultural Adjustment Act of 1938, as amended, unless the Secretary of Agriculture calls for an increase in production of such commodity in the interest of national security.

SEC. 5. The provision of land, facilities, and project modifications which furnish outdoor recreation

project, heretofore authorized in section 9 of the Flood Control Act of December 22, 1944 (58 Stat. 887), as modified by the report of the Secretary of the Interior contained in House Document Numbered 325, Eighty-sixth Congress, second session, is confirmed and approved under the designation "Garrison diversion unit," and the construction of a development providing for the irrigation of two hundred and fifty thousand acres, municipal and industrial water, fish and wildlife conservation and development, recreation, flood control, and other project purposes shall be prosecuted by the Department of the Interior substantially in accordance with the plans set out in the Bureau of Reclamation report dated November 1962 (revised February 1965) supplemental report to said House Document Numbered 325.

SEC. 2. (a) Subject to the provisions of subsections (b), (c), (d), and (e) of this section, the Secretary is authorized in connection with the Garrison diversion unit (i) to construct, operate, and maintain or provide for the construction, operation, and maintenance of public outdoor recreation and fish and wildlife enhancement facilities, (ii) to acquire or otherwise to include within the unit area such adjacent lands or interests in land as are necessary for present or future public recreation or fish and wildlife use, (iii) to allocate water and reservoir capacity to recreation and fish and wildlife enhancement, and (iv) to provide for the public use and enjoyment of unit lands, facilities, and water areas in a manner coordinated with other unit purposes. The Secretary is further authorized to enter into agreements with Federal agencies or State or local public bodies for the operation, maintenance, and replacement of unit facilities, and to transfer unit lands or facilities to Federal agencies or State or local public bodies by lease or exchange, upon such terms and conditions as will best promote the development and operation of such lands or facilities in the public interest for recreation and fish and wildlife enhancement purposes.

(b) All costs allocated to fish and wildlife enhancement and incurred in connection with waterfowl refuges and waterfowl production areas proposed for Federal administration shall be nonreimbursable.

(c) (1) If, before commencement of construction of the unit, non-Federal public bodies agree to administer for recreation or fish and wildlife enhancement or for both of these purposes pursuant to the plan for the development of the unit approved by the Secretary, land and water areas which are not included within Federal waterfowl refuges and waterfowl production areas and to bear not less than one-half the separable costs of the unit allocated to either or both of said purposes, as the case may be, and attributable to such areas and all the costs of operation, maintenance, and replacement incurred in connection therewith, the remainder of the separable capital costs so allocated and attributed shall be nonreimbursable.

(2) In the absence of such a preconstruction agreement, recreation and fish and wildlife enhancement facilities (other than minimum facilities for the public health and safety at reservoir access points and facilities related to Federal waterfowl refuges and waterfowl production areas) shall not be provided, and the allocation of unit costs shall reflect only the number of visitor days

and the value per visitor day estimated to result from such diminished recreation development without reference to lands which may be provided pursuant to subsection (e) of this section.

(d) The non-Federal share of the separable capital costs of the unit allocated to recreation and fish and wildlife enhancement shall be borne by non-Federal interests, under either or both of the following methods as may be determined appropriate by the Secretary: (i) payment, or provision of lands, interests therein, or facilities for the unit; or (ii) repayment, with interest, within fifty years of first use of unit recreation or fish and wildlife enhancement facilities: Provided, That the source of repayment may be limited to entrance and user fees or charges collected at the unit by non-Federal interests if the fee schedule and the portion of fees dedicated to repayment are established on a basis calculated to achieve repayment as aforesaid and are made subject to review and renegotiation at intervals of not more than five

years.

(e) Nothwithstanding the absence of preconstruction agreements as specified in subsection (c) of this section lands may be acquired in connection with construction of the unit to preserve the recreation and fish and wildlife enhancement potential of the unit.

(1) If non-Federal public bodies agree within ten years after initial unit operation to administer for recreation and fish and wildlife enhancement pursuant to the plan for development of the unit approved by the Secretary land and water areas which are not included within Federal waterfowl refuges and waterfowl production areas and to bear not less than one-half the costs of lands acquired therefor pursuant to this subsection and facilities and project modifications provided for those purposes and all costs of operation, maintenance, and replacement incurred therefor, the remainder of the costs of such lands, facilities, and project modifications shall be nonreimbursable. Such agreement and subsequent development shall not be the basis for any allocation of joint costs of the unit to recreation or fish and wildlife enhancement.

(2) If, within ten years after initial operation of the unit, there is not an executed agreement as specified in paragraph (1) of this subsection, the Secretary may utilize the lands for any lawful purpose within the jurisdiction of the Department of the Interior, or may transfer custody of the land to another Federal agency for use for any lawful purpose within the jurisdiction of that agency, or may lease the lands to a non-Federal public body, or may transfer the lands to the Administrator of General Services for disposition in accordance with the surplus property laws of the United States. In no case shall the lands be used or made available for use for any purpose in conflict with the purposes for which the project was constructed, and in every case preference shall be given to uses which will preserve and promote the recreation and fish and wildlife enhancement potential of the project or, in the absence thereof, will not detract from that potential.

(f) Subject to the limitations hereinbefore stated, joint capital costs allocated to recreation and fish and wildlife enhancement shall be nonreimbursable.

(g) Costs of means and measures to prevent loss

of and damage to fish and wildlife shall be treated as unit costs and allocated among all unit purposes.

(h) As used in this Act, the term "nonreimbursable" shall not be construed to prohibit the imposition of entrance, admission, and other recreation user fees or charges.

SEC. 3. The Garrison diversion unit shall be integrated physically and financially with the other Federal works constructed or authorized to be constructed under the comprehensive plan approved by section 9 of the Act of December 22, 1944, as amended and supplemented. The Secretary shall give consideration to returning to the Missouri River to the fullest extent practicable such of the return flows as are not required for beneficial purposes.

SEC. 4. (a) The interest rate used for computing interest during construction and interest on the unpaid balance of the capital costs allocated to interest-bearing features of the Garrison diversion unit as authorized in this Act shall be determined by the Secretary of the Treasury as of the beginning of the fiscal year in which construction is initiated, on the basis of the computed average interest rate payable by the Treasury upon its outstanding marketable public obligations, which are neither due nor callable for redemption for fifteen years from date of issue.

(b) From and after July 1, 1965, the interest rate on the unamortized balance of the investment allocated to commercial power in facilities constructed or under construction on June 30, 1965, by

the Department of the Army in the Missouri River Basin, the commercial power from which is marketed by the Department of the Interior, and in the transmission and marketing facilities associated therewith, shall be 22 per centum per annum.

SEC. 5. For a period of ten years from the date of enactment of this Act, no water from the project authorized by this Act shall be delivered to any water user for the production on newly irrigated lands of any basic agricultural commodity, as defined in the Agricultural Act of 1949, or any amendment thereof, if the total supply of such commodity for the marketing year in which the bulk of the crop would normally be marketed is in excess of the normal supply as defined in section 301(b) (10) of the Agricultural Adjustment Act of 1938, as amended, unless the Secretary of Agriculture calls for an increase in production of such commodity in the interest of national security.

SEC. 6. There is hereby authorized to be appropriated for construction of the Garrison diversion unit as authorized in this Act, the sum of $207,000,000, plus or minus such amounts, if any, as may be justified by reason of ordinary fluctuations in construction costs as indicated by engineering cost indexes applicable to the types of construction involved herein. There are also authorized to be appropriated such additional sums as may be required for operation and maintenance of the unit.

Approved August 5, 1965.

21. Mid-State Division, Missouri River Basin Project, Nebraska Act of Nov. 17, 1965, P.L. 90-136 (81 Stat. 444 et seq.)

AN ACT

To authorize the Secretary of the Interior to construct, operate, and maintain the Nebraska Mid-State division, Missouri River Basin project, and for other purposes.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the Secretary of the Interior is hereby authorized to construct, operate, and maintain in accordance with the Federal reclamation laws (Act of June 17, 1902 (32 Stat. 388), and Acts amendatory thereof or supplementary thereto) the Nebraska Mid-State division, Missouri River Basin project, Nebraska, for the principal purposes of furnishing a surface irrigation water supply for approximately one hundred and forty thousand acres of land, aiding in the replenishment of the ground water supply of the area for domestic and agricultural use, controlling floods, conserving and developing fish and wildlife, enhancing recreation opportunities, and producing hydroelectric power. The principal works of the project shall consist of a diversion dam on the Platte River, a main supply canal, an interconnected reservoir system, hydroelectric power facilities, wasteways, pumps, drains, canals, laterals, distribution facilities, and related works.

SEC. 2. The Nebraska Mid-State division shall be integrated, physically and financially, with the other Federal works in the Missouri River Basin constructed or authorized to be constructed under

the comprehensive plans approved by section 9 of the Act of December 22, 1944 (58 Stat. 891), as amended and supplemented, and shall be a division of the Missouri River Basin project therein approved and authorized.

SEC. 3. The interest rate used for computing interest during construction and interest on the unpaid balance of the capital costs allocated to interest-bearing features of the Nebraska Mid-State division shall be determined by the Secretary of the Treasury as of the beginning of the fiscal year in which construction is initiated, on the basis of the computed average interest rate payable by the Treasury upon its outstanding marketable public obligations, which are neither due nor callable for redemption for fifteen years from date of issue.

SEC. 4. For a period of ten years from the date of enactment of this Act, no water from the project authorized by this Act shall be delivered to any water user for the production on newly irrigated lands of any basic agricultural commodity, as defined in the Agricultural Act of 1949, or any amendment thereof, if the total supply of such commodity for the marketing year in which the bulk of the crop would normally be marketed is in excess of the normal supply as defined in section 301(b) (10) of the Agricultural Adjustment Act of 1938, as amended, unless the Secretary of Agriculture calls for an increase in production of such commodity in the interest of national security.

SEC. 5. The provision of land, facilities, and project modifications which furnish outdoor recreation