Sidebilder
PDF
ePub

be borne in mind that it is almost impossible to determine by a few inspections, even if carried out with great care, that animals are free from ticks. If the treatment is discontinued and a few unobserved ticks are still on the animals, these, on maturing and dropping, are likely to give rise to a new brood of young ticks. Moreover, even if the cattle are actually free from ticks, the fact should not be lost sight of that there may still be engorged females, eggs and seed ticks on the premises. This is most likely to be the case during the colder part of the year when the development of the tick on the ground progresses slowly and also when any seed ticks that may be present are likely to be slow in reaching the cattle because of inactivity resulting from the low temperature.

TO RE-ENFORCE THE ARSENICAL DIPPING SOLUTION IN A VAT, FROM TIME TO TIME WHEN IN USE.

Measure the water poured in to fill up the vat. Then figure the amounts of the materials necessary for that quantity of water. These will be found to be about as follows:

[blocks in formation]

The concentrated solution for the smaller quantities should be prepared in the same manner as when filling the vat the first time, using the proportionate quantities of water.

Specifications for the Construction of a Concrete Cattle-Dipping Vat.

SITE.

The site selected for the location of the vat should be dry and of sufficient size to admit of the construction of

the chute, the dripping pen, and at least two additional pens-one for holding the cattle prior to dipping and the other for retaining them after dipping until sufficiently dried.

EXCAVATION.

The excavation should be made 1 foot wider and 1 foot longer than the inside dimensions of the vat and should conform to its shape. The inside dimensions of the vat are shown on the drawings (fig. I) and are as follows: Lenth at top of vat, 26 feet; bottom, 12 feet. Width at top, 3 feet; at bottom, 12 feet. Depth, 62 feet.

The sides and bottom of the excavation should be firm and solid, as they are to serve for the outside forms in casting the concrete. If it is necessary to do any filling in order to conform to the shape of the vat, the filling should be puddled and thoroughly rammed until solid, because the stability of the concrete depends on the foundation.

FORMS.

The wooden forms should be constructed of 1-inch boards and 2 x 4-inch braces, the boards being nailed to the outside face of the braces as shown in the drawings. The sides and end walls should be built 8 inches higher than the surface of the ground, which should be level.

CONCRETE.

The concrete should be made of 1 part cement, by measure, 211⁄2 parts of sand, and 5 parts of broken rock or gravel. The cement should be of a standard brand of Portland, the sand clean and coarse, and the broken rock from about 1/4-inch pieces to not larger than will pass in every direction througr a 1-inch ring.

Mixing. The mixing should be done on a tight wooden platform or in a tight box. The sand and stone should be measued in a bottomless box, 22 feet long by 2 feet wide by 1 foot deep, having a capacity of 5 cubic feet. A convenient size of batch to mix is one consisting of 2 bags cement, 1 measure (5 cubic feet) of sand, and 2 measures (10 cubic feet) of stone.

[graphic][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

FIG. 1.-Plans for a concrete dipping vat.

SKELETON PRAME

The sand is measured out first and the cement emptied on top, after which the two materials are thoroughly mixed together, dry. In the meantime the stone may be measured out and thoroughly drenched with water. The cement-sand mixture is mixed with water and the resulting mortar then combined with the stone. The stone should be shoveled on the mortar, which has been previously spread out in a thin layer. Mixing should continue until the stone is thoroughly coated with mortar, more water being added during the mixing process if necessary.

Laying. Before laying the concrete the molds should be set and thoroughly braced into place. The side forms may be suspended in the excavation with their lower edges 6 inches from the bottom by means of crosspieces nailed to the uprights and of sufficient length to rest on supports located several feet from the edges of the excavation. The concrete for the bottom and incline is deposited first, this mixture being of a consistency that water will flush to the surface on ramming. The mixtures for the sides and end should be very wet and should be thoroughly puddled into place. The consistency of the concrete for the side walls should be such that it will run off the shovel unless handled quickly.

The laying of the concrete should be done, if possible, in one operation, in order that there may be no joints between the new and old work. If it becomes necessary to lay the concrete on two or more days the surface on which the new concrete is to be deposited should be washed thoroughly clean and coated with grout of pure Portland cement and water mixed to the consistency of cream. The new concrete should be placed before the grout has set. Extreme care should be taken to prevent dirt from falling in on top of the deposited concrete.

The form should not be removed until the concrete is set, which in moderate weather will have taken place in about 24 hours. In damp, cold weather at least 48 hours

[ocr errors]
« ForrigeFortsett »