Cases and Materials on Government ContractsHeadquarters, Department of the Army, 1962 - 567 sider |
Inni boken
Resultat 1-5 av 54
Side 49
... complete ratification . ” Such being the declared law of public agency , what are the facts of this case to which the law must be applied ? In 1875 the work of improving the navigation of the Tennessee had been placed under the charge ...
... complete ratification . ” Such being the declared law of public agency , what are the facts of this case to which the law must be applied ? In 1875 the work of improving the navigation of the Tennessee had been placed under the charge ...
Side 50
... completing their work be extended , and in September he again granted a further extension . During the progress of this extra work the appropriation was transferred to the hands of the engineer in charge , and payments were made to the ...
... completing their work be extended , and in September he again granted a further extension . During the progress of this extra work the appropriation was transferred to the hands of the engineer in charge , and payments were made to the ...
Side 60
... complete examination into the cross - claim , despite attendant disloca- tion of government business by the appearance of important officers at distant points and the production of documents as evidence , to justify the allowance of an ...
... complete examination into the cross - claim , despite attendant disloca- tion of government business by the appearance of important officers at distant points and the production of documents as evidence , to justify the allowance of an ...
Side 71
... completing the removal of its operations from the pier on September 17 , 1942 , the plaintiff continued to refine and process tung- sten for Metals Reserve at the new Glen Cove plant . The Govern- ment stipulated in this case that ...
... completing the removal of its operations from the pier on September 17 , 1942 , the plaintiff continued to refine and process tung- sten for Metals Reserve at the new Glen Cove plant . The Govern- ment stipulated in this case that ...
Side 94
... complete remedy . " We are of opinion that no legal rights of respondents were shown to have been invaded or threatened in the complaint upon which the injunction of the Court of Appeals was based . It is by now clear that neither ...
... complete remedy . " We are of opinion that no legal rights of respondents were shown to have been invaded or threatened in the complaint upon which the injunction of the Court of Appeals was based . It is by now clear that neither ...
Vanlige uttrykk og setninger
accepted action Administration agency agent agreement alleged amount appeal appellant's appellee applied Army Article ASBCA authority award bidder Board breach Brookridge certiorari claimant clause Clearfield Trust Co Company compensation Congress construction contract price contracting officer Corp counterclaim Court of Claims decision default defendant delay delivered the opinion delivery Department determination dispute District Court excess costs fact failure federal furnished Government contract Government's immunity issued J. C. Penney judgment jurisdiction Justice L.Ed labor lease liability liquidated damages materials ment obligation Outer Harbor paid parties payment performance petition petitioners Philadelphia Quartermaster Depot plaintiff Pollia procurement profit purchase pursuant Quartermaster question reason regulations repurchase respondent S.Ct Secretary Section Small Business Administration sovereign immunity specifications Stat statute subcontractor suit Supp supplies supra Supreme Court surety termination tion tract Tucker Act U.S. Ct United
Populære avsnitt
Side 27 - ... express or implied agreement of the parties, acceptance of the goods by the buyer shall not discharge the seller from liability in damages or other legal remedy for breach of any promise or warranty in the contract to sell or the sale. But, if, after acceptance of the goods, the buyer fails to give notice to the seller of the breach of any promise or warranty within a reasonable time after the buyer knows, or ought to know of such breach, the seller shall not be liable therefor.
Side 273 - The rights and remedies of the Government provided in this clause shall not be exclusive and are In addition to any other rights and remedies provided by law or under this contract.
Side 85 - The case is here on a petition for a writ of certiorari which we granted because of the importance of the problem and the contrariety of views in the courts.
Side 111 - When immediate delivery or performance is required by the public exigency the articles or service required may be procured by open purchase or contract at the places and in the manner in which such articles are usually bought and sold, or such services engaged, between individuals.
Side 285 - ... by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule.
Side 32 - A promise which the promisor should reasonably expect to induce action or forbearance of a definite and substantial character on the part of the promisee and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise.
Side 45 - Whatever the form in which the government functions, anyone entering into an arrangement with the Government takes the risk of having accurately ascertained that he who purports to act for the Government stays within the bounds of his authority. The scope of this authority may be explicitly defined by Congress or be limited by delegated legislation, properly exercised through the rule-making power. And this is so even though, as here, the agent himself may have been unaware of the limitations upon...
Side 38 - ... in good faith relied upon such conduct, and has been led thereby to change his position for the worse, and who on his part acquires some corresponding right either of property, of contract, or of remedy.
Side 144 - States, that the measure of damages is the difference between the contract price and the market value of the...
Side 276 - ... unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes...