I. Where the Government draws specifications which are fairly susceptible of a certain construction and the contractor so construes them, justice and equity require that construction to be adopted. Peter Kiewit Sons' Company (No. 46432), 390.
II. Where one of the parties to a contract draws the docu- ment and uses language which is susceptible of more than one meaning, and the intention of the parties does not otherwise appear, that meaning will be given the document which is more favorable to the party who did not draw it; and this rule is especially applicable to a Government contract where the contractor has nothing to say as to its provisions. Noonan v. Bradley, 9 Wall. 407; Chambers v. United States, 24 C. Cls. 387; Callahan Construction Co. v. United States, 91 C. Cls. 538, 611; Blair v. United States, 99 C. Cls. 71, 135; 321 U. S. 730. Id.
See Contracts XXXVIII, LXXVII.
AUTHORITY PRESUMED.
See Personal Injury I, II, III.
See Taxes IV, V, VI.
CANCELLATION OF CONTRACT.
See Contracts XV, XVI, XVII.
CIVIL SERVICE.
See Suit For Salary IX, X, XI, XII, XIII, XIV, XV, XVI, XVII,
CLAIM OF RIGHT.
See Taxes V.
CLASSIFICATION, EFFECTIVE DATE.
See Suit For Salary XVI, XVII, XVIII. CONGRESS, INTENTION OF.
See Suit For Salary XVIII. CONSEQUENTIAL DAMAGE. See Taking II.
CONTRACTING OFFICER.
I. Whether or not the contract required plaintiff to pay the increased wages to common laborers was not a question of fact but of law; and the contract did not require plaintiff to appeal to the contracting officer a ruling of the project engineer on the legal inter- pretation of the contract. Paretta Construction Company, 324.
CONTRACTING OFFICER-Continued
II. The provision of the contract in suit that the decision of the contracting officer as to the proper interpreta- tion of all drawings and specifications should be final, subject to appeal, cannot be employed to oust the jurisdiction of the Court of Claims to construe the legal effect of those provisions of the specifications which are in seeming conflict and to determine the question of law involved. Stafford, 479.
See also Contracts LXVII, LXXI, LXXVII.
I. Where contractor entered into a contract with the Government for road construction, which it was unable to complete within the specified contract time; and where the Government did not terminate the contract, as requested, but issued a suspension order, and the contractor, after the suspension, resumed performance and completed the performance; it is held that the contract remained in force, including its provision for liquidated damages, and plaintiff, surety, is not entitled to recover. United States v. American Surety Company, 322 U. S. 96, distin- guished. Dineen, Supt., 18.
II. The difficulty of determining exact damages is the reason and justification for the insertion of the agreement for liquidated damages. See Lebanon Woolen Mills, Inc. v. The United States, 99 C. Cls. 318.
III. In a suit against the Government seeking a refund of a portion of the transportation and marine insurance charges on articles sold to defendant for shipment to the Canal Zone, the Court of Claims takes judicial notice that on December 30, 1941, when the invita- tion for bids was issued, the United States was at war with both Germany and Japan, and that German submarines were at large in the Atlantic Ocean. Ellicott Machine Corporation, 62.
IV. While the contract obligated plaintiff to include war risk insurance as a part of the shipping costs, neither the contract for shipper to supply dredging parts to be delivered free of all charges at Cristobal, Canal Zone, nor invitation for bids, nor change order issued by the United States, on account of wartime sub- marine menace to shipping, permitting delivery to be made at shipper's plant instead of at Cristobal
and allowing deduction from payments to shipper of shipping costs, obligated shipper to assume cost of marine insurance, which the Government deducted from final settlement and plaintiff is entitled to recover on this item of its claim. Id.
V. Where the invitation for bids to supply dredging parts for delivery at Cristobal, Canal Zone, requiring ship- ments through New York to be routed by a specific steamship line, did not restrict shipments to a route by way of New York but left the port optional to shipper; and where, after the submarine menace closed New York ports to shipping and a change order was issued providing for delivery at plaintiff's plant and providing that shipping costs which would otherwise have been paid by shipper would be de- ducted from payments to shipper; then the deduc- tions could be made according to the cost of ship- ment from available ports and were not restricted to cost of shipment by way of New York, and on this item of its claim plaintiff is not entitled to recover. Id. VI. Where the plaintiff pursuant to proper renegotiation
proceedings entered into agreements with the Gov- ernment relating to the elimination of excessive profits and as a result of these agreements repaid to the Government certain sums; the Court of Claims, having no jurisdiction to determine excessive profits, cannot bar recovery since à ruling barring plaintiff in the instant case would in effect be a ruling that any compensation due plaintiff was an excessive profit. Id.
VII. Where the plaintiffs, in response to identical announce-
ments promulgated by the Government, severally entered into contracts with the Government, through the Federal Surplus Commodities Corpora- tion, for the sale and delivery of stipulated quantities of flour; and where from the announcement and the offers filled out on forms prepared by the Govern- ment, as well as from other documents in evidence, it is established that weekly deliveries were contem- plated during the periods covered by the respective contracts, deliveries to be made in accordance with weekly shipping instructions to be furnished by the Government; and where it was provided in each of the contracts that storage charges were to be paid by the defendant in the event of delay in giving shipping instructions; it is held that the storage charges, under
the terms of the agreements, should be dated and paid from the end of the grace period, 21 days after the contemplated weekly shipments, and not 21 days after the final specified delivery date, and plaintiffs are entitled to recover. Flour Mills of America, Inc., et al., 116.
VIII. Taking into consideration not only the provisions of the several agreements but also all the memoranda, letters and statements, the court concludes that the plaintiffs were entitled to receive some sort of weekly shipping instructions, failing which the Government was obligated to pay the minimum of the storage charges in accordance with the terms of the con- tract.
IX. Except in Case No. 46451, in which the plaintiff is The International Milling Company, the respective con- tracts did not require that the Government order the delivery of the flour in equal quantities weekly. Id. X. It is a cardinal rule of construction of contracts that the court will, if possible, ascertain and give effect to the mutual intention of the parties. Chesapeake and Ohio Canal Co. v. Hill, 15 Wall. 94; Great Northern Ry. Co. v. United States, 236 Fed. 433. Id.
XI. In a suit involving the construction of contracts pro- viding for the sale to the Government of flour, it is necessary and proper to consider the customs and practices of the trade in arriving at the intention of the parties to the contracts. See Hostetter v. Park, 137 U. S. 30; Moore v. United States, 196 U. S. 157, 38 C. Cls. 590. Id.
XII. The fact that contracts, insofar as they are in written form, were prepared by the defendant, may be con- sidered in construing them. Phoenix Insurance Co. v. Slaughter, 12 Wall. 404; Marietta Manufacturing Co. v. United States, 73 C. Cls. 528. Id.
XIII. An essential element of a contract is mutuality; and the corresponding obligation of the defendant may be express or implied. Butler v. Thompson, 92 U. S. 412. Id.
XIV. Since the Government has given its consent to be sued in contract cases, it is, as the defendant, not an exception to the rule that obligations assumed by the contract must be mutual. There is no reason why the Government, in such cases, should be treated as a favored litigant. See Sacramento Navigation Company v. Salz, 273 U. S. 326; 17 Corpus Juris, Secundum, Section 328. Id.
XV. In a suit for material furnished and work performed under a Government contract which was canceled by the Government before completion; it is held that the defendant is bound by the letter of the con- tracting officer of June 6, 1942, notifying the plaintiff that the contract was canceled under Article 23 of the contract, and plaintiff is entitled to recover. Line Construction Company, 154.
XVI. A subsequent letter, dated June 9, 1942, notifying the contractor that its right to proceed was not termi- nated in accordance with Article 23 of the contract but under the provisions of Article 9, due to its failure to commence operations and maintain the rate of progress stipulated in Article 1 thereof, was of no effect since the letter of June 9 was apparently not received until June 12 and the contractor had meantime, on June 10, acknowledged the letter of June 6 and complied with the order of the contract- ing officer to furnish to him inventories of materials, apparatus and equipment delivered to the job, which materials, supplies and equipment were sub- sequently used by the successor contractor in com- pleting the job. Id.
XVII. In the instant case there is no question of mutual mistake, since the contracting officer testified that he read carefully the letter of June 6 and under- stood its contents and importance. There is no claim that plaintiff or any of its representatives un- dertook to mislead the defendant. The letter of June 6 was carefully prepared; its contents were not shown to the plaintiff before transmission. It does not come within the limits of any exceptions laid down in the books whereby a man may escape the consequences of his act. See Wigmore On Evidence, Vol. 4, section 2415, and cases there cited. Id. XVIII. The court holds that the defendant is not entitled to recover on its cross action against plaintiff for the excess cost of completion of the job by the succeeding contractor less the allowance for materials and equipment, and work completed, since the contract was canceled under Article 23 of the contract and the provisions of Article 9, as to termination of plaintiff's right to proceed due to failure to com- mence operations and to maintain the required rate of progress, were not effective. Id.
« ForrigeFortsett » |