and allowing deduction from payments to shipper of shipping costs, obligated shipper to assume cost of marine insurance, which the Government deducted from final settlement and plaintiff is entitled to recover on this item of its claim. Id. V. Where the invitation for bids to supply dredging parts for delivery at Cristobal, Canal Zone, requiring ship- ments through New York to be routed by a specific steamship line, did not restrict shipments to a route by way of New York but left the port optional to shipper; and where, after the submarine menace closed New York ports to shipping and a change order was issued providing for delivery at plaintiff's plant and providing that shipping costs which would otherwise have been paid by shipper would be de- ducted from payments to shipper; then the deduc- tions could be made according to the cost of ship- ment from available ports and were not restricted to cost of shipment by way of New York, and on this item of its claim plaintiff is not entitled to recover. Id. VI. Where the plaintiff pursuant to proper renegotiation proceedings entered into agreements with the Gov- ernment relating to the elimination of excessive profits and as a result of these agreements repaid to the Government certain sums; the Court of Claims, having no jurisdiction to determine excessive profits, cannot bar recovery since a ruling barring plaintiff in the instant case would in effect be a ruling that any compensation due plaintiff was an excessive profit. Id.
VII. Where the plaintiffs, in response to identical announce- ments promulgated by the Government, severally entered into contracts with the Government, through the Federal Surplus Commodities Corpora- tion, for the sale and delivery of stipulated quantities of flour; and where from the announcement and the offers filled out on forms prepared by the Govern- ment, as well as from other documents in evidence, it is established that weekly deliveries were contem- plated during the periods covered by the respective contracts, deliveries to be made in accordance with weekly shipping instructions to be furnished by the Government; and where it was provided in each of the contracts that storage charges were to be paid by the defendant in the event of delay in giving shipping instructions; it is held that the storage charges, under
the terms of the agreements, should be dated and paid from the end of the grace period, 21 days after the contemplated weekly shipments, and not 21 days after the final specified delivery date, and plaintiffs are entitled to recover. Flour Mills of America, Inc., et al., 116.
VIII. Taking into consideration not only the provisions of the several agreements but also all the memoranda, letters and statements, the court concludes that the plaintiffs were entitled to receive some sort of weekly shipping instructions, failing which the Government was obligated to pay the minimum of the storage charges in accordance with the terms of the con- tract. Id.
IX. Except in Case No. 46451, in which the plaintiff is The International Milling Company, the respective con- tracts did not require that the Government order the delivery of the flour in equal quantities weekly. Id. X. It is a cardinal rule of construction of contracts that the court will, if possible, ascertain and give effect to the mutual intention of the parties. Chesapeake and Ohio Canal Co. v. Hill, 15 Wall. 94; Great Northern Ry. Co. v. United States, 236 Fed. 433. Id. XI. In a suit involving the construction of contracts pro- viding for the sale to the Government of flour, it is necessary and proper to consider the customs and practices of the trade in arriving at the intention of the parties to the contracts. See Hostetter v. Park, 137 U. S. 30; Moore v. United States, 196 U. S. 157, 38 C. Cls. 590. Id.
XII. The fact that contracts, insofar as they are in written form, were prepared by the defendant, may be con- sidered in construing them. Phoenix Insurance Co. v. Slaughter, 12 Wall. 404; Marietta Manufacturing Co. v. United States, 73 C. Cls. 528.
Id.
XIII. An essential element of a contract is mutuality; and the corresponding obligation of the defendant may be express or implied. Butler v. Thompson, 92 U. S. 412. Id.
XIV. Since the Government has given its consent to be sued in contract cases, it is, as the defendant, not an exception to the rule that obligations assumed by the contract must be mutual. There is no reason why the Government, in such cases, should be treated as a favored litigant. See Sacramento Navigation Company v. Salz, 273 U. S. 326; 17 Corpus Juris, Secundum, Section 328. Id.
XV. In a suit for material furnished and work performed under a Government contract which was canceled by the Government before completion; it is held that the defendant is bound by the letter of the con- tracting officer of June 6, 1942, notifying the plaintiff that the contract was canceled under Article 23 of the contract, and plaintiff is entitled to recover. Line Construction Company, 154.
XVI. A subsequent letter, dated June 9, 1942, notifying the contractor that its right to proceed was not termi- nated in accordance with Article 23 of the contract but under the provisions of Article 9, due to its failure to commence operations and maintain the rate of progress stipulated in Article 1 thereof, was of no effect since the letter of June 9 was apparently not received until June 12 and the contractor had meantime, on June 10, acknowledged the letter of June 6 and complied with the order of the contract- ing officer to furnish to him inventories of materials, apparatus and equipment delivered to the job, which materials, supplies and equipment were sub- sequently used by the successor contractor in com- pleting the job. Id.
XVII. In the instant case there is no question of mutual mistake, since the contracting officer testified that he read carefully the letter of June 6 and under- stood its contents and importance. There is no claim that plaintiff or any of its representatives un- dertook to mislead the defendant. The letter of June 6 was carefully prepared; its contents were not shown to the plaintiff before transmission. It does not come within the limits of any exceptions laid down in the books whereby a man may escape the consequences of his act. See Wigmore On Evidence, Vol. 4, section 2415, and cases there cited. Id. XVIII. The court holds that the defendant is not entitled to recover on its cross action against plaintiff for the excess cost of completion of the job by the succeeding contractor less the allowance for materials and equipment, and work completed, since the contract was canceled under Article 23 of the contract and the provisions of Article 9, as to termination of plaintiff's right to proceed due to failure to com- mence operations and to maintain the required rate of progress, were not effective. Id.
XIX. 1. In a suit for damages for alleged breaches by the defendant of a construction contract, involving seven buildings the foundations of which were con- structed under a separate contract; it is held that plaintiff is not entitled to recover for delay due to defendant's alleged failure to deliver to plaintiff the respective sites of certain of the buildings at the time set forth in the contract, since the sites were delivered as contemplated by the contract, and, in addition, the defendant did not agree to deliver the sites on any specific dates. See United States v. Foley Co., 329 U. S. 64. Cauldwell-Wingate Com- pany, 193.
XX. Where both plaintiff's contract and the contract for the foundation work contained the usual provisions authorizing the Government to make changes in the drawings or specifications; and where the changes made in the foundation contract were made pur- suant to this provision; it is held that for any delay incident thereto the plaintiff is not entitled to re- cover under the decision in United States v. Rice, 317 U. S. 61. Id. XXI. 2. Where the shop drawings for doors as originally submitted did not comply with the specifications, and for that reason were not originally approved, but upon plaintiff's insistence were finally approved in order to prevent further delay; it is held that the defendant was not responsible for this delay and plaintiff is not entitled to recover. Id.
XXII. 3. Where it is found that the defendant's inspector's requirement that blemishes be removed from con- crete ceilings in the houses was not unreasonable but in accordance with the provisions of the con- tract; it is held that plaintiff is not entitled to recover for the cost of extra work involved in removing the blemishes. Id. XXIII. 4. Where defendant's project manager had approved
the drawings submitted by plaintiff with reference to the installation of rawl drives in anchoring the plaster partitions; and where defendant's inspector, in spite of the approval by the project manager, re- quired the installation of additional rawl drives, which he had no authority to do; and where plain- tiff acceded to the inspector's demand without protesting to the contracting officer; it is held that plaintiff is barred from recovery on account of its
failure to protest. See United States v. Blair, 321 U. S. 730; Silas Mason Co. v. United States. 105 C. Cls. 27. Id.
XXIV. 5. Where, after amended instructions were given with reference to the inspector's requirement that the plastered partitions be exactly plumb and true, plaintiff made no further written protest against the requirements of the inspectors and also failed to take any appeal to the head of the department from the adverse ruling of the contracting officer on its claim; it is held that plaintiff is not entitled to recover on this item. Id.
XXV. 6. Where plaintiff made no protest against most of the requirements of the inspectors; and where in no case did plaintiff take an appeal to the head of the department from the adverse ruling of the contracting officer, as required under Article 15 of the contract; the court, after careful examination of plaintiff's other claims, in which no merit is discovered, holds that plaintiff is not entitled to recover on any items of its claim. Id.
XXVI. Property rights, as such, are by no means the only
matters the full enjoyment of which may be protected by contract, and for which a contracting party may be required to respond in damages in the event the agreement is breached; and where something other than a strict property right is the object of concern the difficulty of ascertaining the damage in event of breach would appear to make a stipulation as to liquidated damages only the more desirable. See Sun Printing & Publishing Assn. v. Moore, 183 U.-S. 642, 670. Oregon-Washington R. R. & Nav. Co. v. United States, 58 C. Cls. 645, 648, reaffirmed. Weathers Bros. Transfer Co., Inc., 310.
XXVII. In the instant case, in which plaintiff is seeking to be compensated for transporting property not owned by the Government but for the transportation of which the Government had contracted with plaintiff, the plaintiff is saying with respect to defendant's counter- claim that, because the goods transported under a prior contract were not the property of the Govern- ment, plaintiff cannot be required under any circum- stances to respond in damages to the Government for a breach of this prior contract; and the court holds that plaintiff's contention cannot be sustained, and plaintiff is not entitled to recover for liquidated damages deducted under the prior contract. Id.