XIX. 1. In a suit for damages for alleged breaches by the defendant of a construction contract, involving seven buildings the foundations of which were con- structed under a separate contract; it is held that plaintiff is not entitled to recover for delay due to defendant's alleged failure to deliver to plaintiff the respective sites of certain of the buildings at the time set forth in the contract, since the sites were delivered as contemplated by the contract, and, in addition, the defendant did not agree to deliver the sites on any specific dates. See United States v. Foley Co., 329 U. S. 64. Cauldwell-Wingate Com- pany, 193.
XX. Where both plaintiff's contract and the contract for the foundation work contained the usual provisions authorizing the Government to make changes in the drawings or specifications; and where the changes made in the foundation contract were made pur- suant to this provision; it is held that for any delay incident thereto the plaintiff is not entitled to re- cover under the decision in United States v. Rice, 317 U. S. 61. Id.
XXI. 2. Where the shop drawings for doors as originally submitted did not comply with the specifications, and for that reason were not originally approved, but upon plaintiff's insistence were finally approved in order to prevent further delay; it is held that the defendant was not responsible for this delay and plaintiff is not entitled to recover. Id.
XXII. 3. Where it is found that the defendant's inspector's requirement that blemishes be removed from con- crete ceilings in the houses was not unreasonable but in accordance with the provisions of the con- tract; it is held that plaintiff is not entitled to recover for the cost of extra work involved in removing the blemishes. Id.
XXIII. 4. Where defendant's project manager had approved the drawings submitted by plaintiff with reference to the installation of rawl drives in anchoring the plaster partitions; and where defendant's inspector, in spite of the approval by the project manager, re- quired the installation of additional rawl drives, which he had no authority to do; and where plain- tiff acceded to the inspector's demand without protesting to the contracting officer; it is held that plaintiff is barred from recovery on account of its
failure to protest. See United States v. Blair, 321 U. S. 730; Silas Mason Co. v. United States. 105 C. Cls. 27. Id.
XXIV. 5. Where, after amended instructions were given with reference to the inspector's requirement that the plastered partitions be exactly plumb and true, plaintiff made no further written protest against the requirements of the inspectors and also failed to take any appeal to the head of the department from the adverse ruling of the contracting officer on its claim; it is held that plaintiff is not entitled to recover on this item. Id.
XXV. 6. Where plaintiff made no protest against most of the requirements of the inspectors; and where in no case did plaintiff take an appeal to the head of the department from the adverse ruling of the contracting officer, as required under Article 15 of the contract; the court, after careful examination of plaintiff's other claims, in which no merit is discovered, holds that plaintiff is not entitled to recover on any items of its claim. Id.
XXVI. Property rights, as such, are by no means the only matters the full enjoyment of which may be protected by contract, and for which a contracting party may be required to respond in damages in the event the agreement is breached; and where something other than a strict property right is the object of concern the difficulty of ascertaining the damage in event of breach would appear to make a stipulation as to liquidated damages only the more desirable. See Sun Printing & Publishing Assn. v. Moore, 183 U.-S. 642, 670. Oregon-Washington R. R. & Nav. Co. v. United States, 58 C. Cls. 645, 648, reaffirmed. Weathers Bros. Transfer Co., Inc., 310.
XXVII. In the instant case, in which plaintiff is seeking to be compensated for transporting property not owned by the Government but for the transportation of which the Government had contracted with plaintiff, the plaintiff is saying with respect to defendant's counter- claim that, because the goods transported under a prior contract were not the property of the Govern- ment, plaintiff cannot be required under any circum- stances to respond in damages to the Government for a breach of this prior contract; and the court holds that plaintiff's contention cannot be sustained, and plaintiff is not entitled to recover for liquidated damages deducted under the prior contract. Id.
XXVIII. If it is true that the Government may obligate itself to furnish transportation for property not its own, such as household goods of Army officers, as in the instant case, and be required to pay for such trans- portation at the rates provided for the carrying of private property; then, and in that event, the Gov- ernment may fairly contract to protect such non- property interest as it may have in the goods trans- ported. Id.
XXIX. It cannot be reasonably concluded that the Govern- ment did not have a material stake in the undertak- ing by plaintiff to transfer the household goods of certain Army officers within agreed dates, whether its primary concern was for the convenience and welfare of its military personnel whose goods it had undertaken to move or whether it was primarily concerned with the possible disruption of its military operations and the tangible and intangible losses which might accrue to it therefrom. Id.
XXX. 1. Where under the provisions of a contract with the Government for the construction of a part of a hous- ing project, the plaintiff was obligated to pay me- chanics and laborers minimum wages as determined by the Secretary of Labor to be the prevailing wages therefor in the community in which the work was to be done, as required by the Davis-Bacon Act, as amended; and where, at the request of plaintiff and for plaintiff's benefit, the determination of the Secre- tary for wages of carpenters was increased from $1.25 per hour to $1.35 per hour; it is held that the plaintiff is not entitled to recover for the increased labor costs thereby incurred. Albert & Harrison, Inc. v. United States, 107 C. Cls. 292; certiorari denied, 331 U. S. 810, distinguished. Paretta Con- struction Company, 324.
XXXI. 2. Where the contract fixed the minimum wage to be paid common laborers at 65 cents per hour, as deter- mined by the Secretary of Labor for the community; and where, thereafter, under a ruling of the Wage Adjustment Board, permission was given to increase the wage rate of laborers from 65 cents to 80 cents per hour; and where plaintiff declined to pay this in- creased rate until ordered to do so by the project engineer under threat of termination of the contract; it is held that, since the contract required no more than that plaintiff pay a minimum of 65 cents an hour and since the ruling of the Wage Adjustment
Board amounted to no more than permission to pay as much as 80 cents an hour and did not require plaintiff to do so, plaintiff is entitled to recover the increased labor costs thereby incurred. See Em- ployees Group of Motor Freight Carriers v. National War Labor Board, 143 F. (2d) 145. Id.
XXXII. Plaintiff paid the increased wages of common laborers as a result of the wrongful demand of defendant's representative in charge of the work, and hence de- fendant should pay the increased cost resulting therefrom. Id.
XXXIII. In the contract in suit, the contract and specifications did not contain the usual provision relating to a protest to the contracting officer against any ruling of defendant's representative on the job, and in the absence of such a provision the defendant is bound by the wrongful acts of its representative on the job. Id.
XXXIV. Whether or not the contract required plaintiff to pay the increased wages to common laborers was not a question of fact but of law; and the contract did not require plaintiff to appeal to the contracting officer a ruling of the project engineer on the legal inter- pretation of the contract. Id.
XXXV. 3. Under plaintiff's contract to construct the founda- tions, which was provided for under a change order; it is held that plaintiff was obligated to protect the work it had done on the foundations and is not en- titled to recover for the damage to the piers and footings caused by frost. Id.
XXXVI. In a contract with the Government for the construc- tion of a levee along the Illinois River and one of its tributaries, where the contract provided that labor should first be secured from the relief rolls; and where it was not possible to secure skilled and semiskilled labor from this source; and where it is found from the evidence that the contract provision did not cause the plaintiff to use unskilled labor un- economically; it is held that the plaintiff is not en- titled to recover for excessive labor costs in the completion of the contract. Stiers Bros. Construc- tion Company, 353.
XXXVII. In a contract with the the Government for the con- struction of a levee along the Illinois River and one of its tributaries, where it was provided that mate- rial should be taken from depressions between the
levee and the river which were to be filled with spoil from dredging operations being carried on in the river; it is held that there was no misrepresenta- tion as to the contents of the borrow pits and plain- tiff is not entitled to recover. Id.
XXXVIII. Where the plaintiff appealed in writing to the Chief of Engineers from the decision of the contracting officer with respect to changed conditions encoun- tered; and where the Chief of Engineers refused to pass on the merits of the claim because the appeal had not been filed within the time limit prescribed by the contract; it is held that plaintiff is not en- Id.
XXXIX. Upon the evidence presented as to alleged delays by reason of difficulty in securing relief labor, which the contractor claimed caused abandonment of work by a subcontractor and which the contractor also claimed caused the greater employment of hand labor for work which might have been otherwise done by machinery; and upon the showing made that the contractor failed to take advantage of the contract provisions for requesting extensions of time and for filing appeals; it is held that plaintiff is not entitled to recover liquidated damages deducted without protest in final settlement for delays in completion of the contract. Id.
XL. In a contract for the construction of certain buildings at Fort Crook, Nebraska, and for other work, in- cluding certain excavation work, in connection there- with, where the contractors interpreted certain pro- visions of the specifications as providing for pay- ment for excavation within the building lines at $1.29 per cubic yard, as "common excavation," and not at 22 cents per cubic yard, as "unclassified ex- cavation"; it is held that the interpretation placed on the provisions by the contractors was reasonable, and plaintiffs are entitled to recover. Peter Kiewit Sons' Company (No. 46432), 390.
XLI. Where the Government draws specifications which are fairly susceptible of a certain construction and the contractor so construes them, justice and equity require that construction to be adopted. Id.
XLII. Where one of the parties to a contract draws the docu- ment and uses language which is susceptible of more than one meaning, and the intention of the parties does not otherwise appear, that meaning will be
« ForrigeFortsett » |