Skjulte felter
Bøker Bok
" Officer grants a further period of time before the date of final payment under the contract), notifies the ContractIng Officer In writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Cases Decided in the Court of Claims of the United States - Side 346
av United States. Court of Claims - 1948
Uten tilgangsbegrensning - Om denne boken

Cases Decided in the Court of Claims of the United States, Volum 111

United States. Court of Claims - 1948 - 886 sider
...writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Uten tilgangsbegrensning - Om denne boken

Quarters and Allowances at St. Elizabeths Hospital: Hearings Before the ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 252 sider
...cause of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...
Uten tilgangsbegrensning - Om denne boken

Quarters and Allowances at St. Elizabeths Hospital: Hearings, Seventieth ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 266 sider
...cause of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...
Uten tilgangsbegrensning - Om denne boken

Decisions of the Comptroller General of the United States, Volum 8

United States. General Accounting Office - 1929 - 804 sider
...of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts there shall be final and conclusive on the parties hereto, subject only to appeal, within thirty days, by the contractor to the head of the department concerned, whose decision oil such appeal...
Uten tilgangsbegrensning - Om denne boken

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 sider
...delay, who shall ascertain the facts and the (4) ю-im extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty days, by the contractor to the head of the department concerned, whose decision on such appeal...
Uten tilgangsbegrensning - Om denne boken

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 sider
...causes, in the event of such aelay the contacting officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment tne findings of fact justify such an extension, and his findings of fact thereon shall be final and...
Uten tilgangsbegrensning - Om denne boken

Congressional Serial Set, Utgave 9878

1935 - 1036 sider
...contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of delay and his findings of fact thereon shall be final and...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...
Uten tilgangsbegrensning - Om denne boken

Aerial Survey Handbook 1938

United States. Forest Service - 1938 - 76 sider
...delay, who shell rscerta^n the fectr- end the extent of the deluy and extond the time for completine the work when in his judgment the findings of fact justify such an eitension, rnd his findings of fact thereon shell be final and conclusive on the prrties hereto, subject...
Uten tilgangsbegrensning - Om denne boken

The Code of Federal Regulations of the United States of America ..., Bok 2

1939 - 1306 sider
...such notification from the Contractor, the Contracting Officer shall ascertain the cause of the delay, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject to appeal within thirty days by the Contractor to the Secretary of War or his duly authorized representative,...
Uten tilgangsbegrensning - Om denne boken

The Code of Federal Regulations of the United States of America ..., Bok 1

1944 - 1386 sider
...such notification from the Contractor, the Contracting Officer shall ascertain the cause of the delay, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject to appeal within thirty days by the Contractor to the Secretary of War or his duly authorized representative,...
Uten tilgangsbegrensning - Om denne boken




  1. Mitt bibliotek
  2. Hjelp
  3. Avansert boksøk
  4. Last ned ePub
  5. Last ned PDF